MPX Import Options

The default settings allow most MPX files to be imported. Preferences are stored in the map, so that different maps can have different settings.

Click Reset to reset all the options to their default settings.

Working days per week

The number of working days per week is required so that any durations in weeks received in an imported MPX file can be converted to hours in the MindManager map. This value is not used anywhere else within MindManager.

Default Task Priority

The Default task priority option defines the priority value that is used if no priority is defined for the task.

The MPX specification (and most Project Management software packages) does not have an explicit value for "No Priority". All tasks have some kind of priority. Rather than assume that no priority is automatically the lowest priority, the MPX import allows you to specify what priority value should be inferred for a task if not present.

When importing maps from an MPX file, if the priority of a task corresponds to the default task priority value, then no priority is marked on the Topic. This avoids importing maps where all Topics are marked with the same priority; the map is clearer if only the exceptions to "normal" priority are identified.

Use "Clock" Icon to mark Milestones

Most project management packages use zero duration for a Task to indicate a "Milestone" for reporting purposes.

The MPX import can optionally use the "Clock" Icon to visually mark Milestones in the map.

MPX import behavior

Importing MPX files can work in two ways, either importing just the constraint information for the project, or the schedule information. MindManager cannot hold both the constraints and task schedule data at the same time, so a choice must be made.

In addition to the task name and notes, this setting will import

In addition to the Task name and notes, this setting will import

Task Predecessors and Successors

The MPX import can represent information about task Predecessors or Successors in the map by using Relationships. This allows you to visualize the interdependence between tasks, and create a project plan that is much nearer to a realistic schedule than just a list of tasks. Task Successors and Predecessors act as constraints that greatly improve the accuracy and usability of the initial schedule.

This setting has three values:

This setting will ignore any information about Task Successors and Predecessors on import from MPX.

Any task Predecessors or Successors are rendered as Relationships in the map.

Relationships are always drawn from a Task to its Successor (which can also be described as from a Task's Predecessor to the Task).

The Relationship type is added to the relationship as floating text, where it differs from the default relationship type; this may be SS, SF, FS or FF as described below.

If the same Relationship is defined more than once in the MPX file (e.g. Task A is shown as a Predecessor to Task B, and Task B is shown as a Successor to Task A), then only one Relationship is added between these two Tasks in the map.

Predecessors and Successors can only be used to connect Tasks, and not Task Summaries or other Topics outside the project tree, which are ignored.

Default Task Relationship type

This option is only valid if the "Task Predecessors and Successors" option is also enabled. Otherwise, it is ignored.

The default type of Task relationship can be defined, so that if a relationship is drawn between two tasks and does not have a specific type attached to it, then the default will be used.

The options available are:

The most common type of task relationship is FS (Finish to Start).

On import, if the Task Predecessors and Successors are being imported to relationships, then if the relationship type matches the current default setting, it is not explicitly marked in the map. This clarifies the map by only showing relationship types that vary from the norm.

Learn more:  Import an MPX file